Microsoft Project for the web will soon become Microsoft Planner. You can continue using most of the Project for the web capabilities in the new Planner once it's rolled out to your organization. Learn more about the new Planner in Frequently asked questions about Planner and Planner help & learning.

Start a new project

  1. In Project Home, select New plan.

  2. Select Untitled project and give your project a name.

    • By default, you are the Project Manager and today is the project Start date, but you can change these as needed.

The New Project pane in Project with a project name and date added

Add tasks and summary tasks

  1. Select Add new task and type a task name. Then press Enter.

  2. Type another task name and press Enter again until you have a full list of tasks.

  3. To indent tasks under summary tasks, select the three vertical dots by the task name and choose Make subtask. Tips:

    • To select more than one task, select a task, press and hold Ctrl, and then select another task.

    • You can also choose Promote subtask to move tasks out from under summary tasks.

The Add New Task selection in Project

The Make Sub-Task menu selection within a project in Project

Assign tasks

To assign tasks, your project needs to be associated with an Office 365 Group. If you’re the project owner, you can:

  • Add your project to a group by choosing Group members at the top of your project.

  • Add or remove people from the project’s group.

To assign a task:

  1. In the Assigned to column for a task, select the person icon.

  2. Choose a team member from the list or enter text to search for one.

The Assigned To column in Project, displaying a name search

For more information on assigning tasks, see Share a project.

Add duration and columns

It's often easiest to begin constructing your project with duration.

  1. In the Duration column for a task, type the number of days you think it will take to accomplish.

    If you want to use a different unit of time, enter a number plus the word hours, weeks, or months.

    If you want your task to appear as a diamond-shaped milestone  Screen shot of a milestone icon in Project for the web in Timeline view, type 0 days in the Duration column.

  2. Press Enter to go to the next task's Duration field and continue entering durations.

You can't enter duration for summary tasks.

You can continue to add more details to your project by adding columns.

  • Beside the Duration column header, choose Add Column.

The Duration column in Project, displaying a duration being entered

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.